Holy Family Parish Renovation

(Holy Family Parish, June - August 2006)

June 2006

Ground floor of Holy Family School which will undergo major renovation this summer:

Girls bathroom will be demolished to make way for two new classrooms:

Current walkway between boys and girls bathrooms (boys bathroom will also be demolished to make way for new restrooms and a small kitchen):

July:

Architect Kevin Broderick and Gary Samaniego inspecting ground floor:

Plumbers working in old boys rest room:

Construction crew removing debris:

Workers preparing area for new rest rooms and kitchen:

Workers preparing ground for two new classrooms:

With former Holy Family School teachers, Sisters Rose & Philomena, current principal, Mr. Glen Lutz:

Electrician working on new bathrooms at Holy Family School:

Area of new parish hall, frames for walls of new classrooms & bathrooms:

Jim Pottmann (on site project director), principal Glen Lutz, architect Keven Broderick and project manager Todd Hartmann:

:

Parking Lots Resealing and Restriping:
:

:

:

:

:

:

:

:

Repair of ceiling of parish hall/gymnasium:

:

:

:

:

:

:

:

:

: